
How and why the Severomuysky tunnel on the BAM was built
There are many interesting pages in the history of the construction of the Baikal-Amur Mainline. This unique infrastructure facility became a grandiose all-Union construction project in the 70s and 80s. Despite the fact that the official opening date of this railway is considered to be 1989, work on many sections continued for decades.
The BAM builders encountered many difficulties along the way. The difficult terrain, climatic features, and lack of funding constantly led to delays. The main long-term construction project was the Severomuysky tunnel through the Angarakan mountain pass.
The BAM was designed and built back in the 1930s. But the outbreak of the Great Patriotic War led to the project being frozen. Even the already laid rails were dismantled and transported to other regions of the country where there was a shortage of communication routes.
In the 40s, engineers assumed that the Severomuysky Ridge could be crossed using an open "winding" railway track and a small tunnel. But in the 70s, a decision was made to dig a long and full-fledged underground passage. Mining operations began in 1977.
Severomuysky tunnel and external bypass on the map. Photo: vkvideo.ru
When passing through the mountain range, the builders had to solve a lot of engineering problems. For example, along the tunnel route, several tectonic faults were discovered from which hot thermal water was constantly flowing. It was necessary to develop and implement a technology for its removal and freezing. Radioactive gas was also found in the mine workings. This also required a certain approach and complicated the work.
There were also human casualties. In the history of tunnel construction, there were several serious incidents related to overcoming mountain ranges. Miners often "ran into" quicksand - unstable rocks and soil. Their sudden movement led to collapses or flooding.
Experts note that such difficult natural conditions during the construction of an underground tunnel have never been encountered anywhere else in the world. But despite all the obstacles, from 1977 to 1991, Soviet engineers and builders managed to pass through over 13 thousand meters of rock. However, they were unable to complete the work before the collapse of the USSR.
The Baikal-Amur Mainline was finally launched in 1989. In order to connect the western and eastern sections of the BAM, the so-called Severomuysky bypass was commissioned back in 1983 – a winding railway with viaducts and small tunnels.
Initially, the bypass was about 25 km long, but then the access roads were widened and the length of the road increased to 64 km. This complex structure required constant repair and maintenance. Speed Train did not exceed 20 km/h. On some sections, locomotives worked in a coupling to "push" heavy carriages up the hill. Passage of passenger trains was strictly prohibited. People were transported by buses across the pass along the BAM automobile backup.
Devil's Bridge on BAM. Photo: vkvideo.ru
Perhaps the most iconic and recognizable object on this section is the Devil's Bridge - a viaduct 360 meters long and 35 meters high. It is located on two-tiered supports, which sway slightly when heavy trains pass. Despite this, the bridge is considered one of the most beautiful man-made objects on the BAM and still attracts travelers and enthusiasts.
It was clear to everyone that the Severomuysky bypass was only a temporary solution. No one gave up on the idea of building a tunnel. But it is important to understand that in the 90s the country had no time for some tunnel on the BAM.
But the work continued with varying degrees of intensity. In total, from 1991 to 2001, the builders covered 2216 meters and were able to perform a joint, that is, to join different sections with minimal divergence. Already in December 2001, the first train passed through the Severomuysky tunnel. But the arrangement work continued for another 2 years.
The entire construction took 26 years. At the same time, the estimated service life of the tunnel is estimated by experts at 100 years.
After completion of construction, the total length of the single-track crossing was 15343 meters. This unique infrastructure facility became the longest railway tunnel in Russia. Today, trains cover this distance in about 25 minutes.
The builders had to meet special requirements for the reliability of all units and structures. The Severomusky tunnel is located in an extremely seismically active area. During the work alone, geologists recorded up to 1,5 thousand earthquakes annually. In addition, the movement of rocks creates colossal loads on the tunnel walls, which also required engineers to take a special approach to the construction of structures.
Access roads to the Severomuysky tunnel. Photo: vkvideo.ru
The water inflow in the spring months reaches 10 thousand m3/hour. Therefore, powerful water drainage installations operate in the tunnel every day, which prevent incoming water from washing out concrete structures and damaging the railway tracks. Engineers have also provided ventilation, which removes not only carbon dioxide from the passage, but also deadly radon.
The Severomuysky crossing is a strategically important facility, which is guarded around the clock by both internal security and special services. In total, up to 16 pairs of trains pass through the tunnel per day. The Severomuysky bypass is also maintained in working order. This is a backup route in case of any emergency situations.
In the context of growing business activity within the country, as well as with the increase in the volume of foreign trade with Asian countries, not long ago there was talk about the necessary modernization of the BAM and the construction of a second railway tunnel.
Work on modernization of BAM. Photo: vkvideo.ru
Indeed, BAM is currently at the peak of its capacity, and the single-track Severomuysky tunnel resembles the narrow neck of an hourglass. Russian Railways has set the task of increasing BAM freight traffic to 100 million tons per year by 2050. But this figure cannot be achieved without building another underground passage in the Severomuysky Ridge area.
Both Russian Railways and a number of large mining companies in Siberia and the Far East are interested in building the new tunnel. Investors have given different figures for the cost of the project – from 60 to 259 billion rubles. But in reality the project could cost more than 500 billion.
In April 2024, on the instructions of the President, Russian Railways and Bamtonnelstroy-Most signed an agreement on the construction of the second Severomuysky tunnel. Work began in May 2024. The project is scheduled to be completed by 2032.
Severomuysky bypass. Photo: vkvideo.ru
After the construction is completed, the capacity of the BAM will increase more than 2-fold, and together with the Trans-Siberian Railway it may even reach 270 million tons per year. There will also be no need to maintain the working condition of the external Severomuysky bypass.
Once upon a time, not all Soviet officials agreed with the need to build the BAM. They did not see any prospects. Today, the issue of increasing the capacity of this railway is acute.
All that remains for us is to thank our ancestors for such a necessary and important infrastructure facility. Let us wish good luck to the new generation of mining engineers who continue to develop the country's transport and logistics potential.
The BAM builders encountered many difficulties along the way. The difficult terrain, climatic features, and lack of funding constantly led to delays. The main long-term construction project was the Severomuysky tunnel through the Angarakan mountain pass.
How the longest tunnel in the Union was built
The BAM was designed and built back in the 1930s. But the outbreak of the Great Patriotic War led to the project being frozen. Even the already laid rails were dismantled and transported to other regions of the country where there was a shortage of communication routes.
In the 40s, engineers assumed that the Severomuysky Ridge could be crossed using an open "winding" railway track and a small tunnel. But in the 70s, a decision was made to dig a long and full-fledged underground passage. Mining operations began in 1977.

When passing through the mountain range, the builders had to solve a lot of engineering problems. For example, along the tunnel route, several tectonic faults were discovered from which hot thermal water was constantly flowing. It was necessary to develop and implement a technology for its removal and freezing. Radioactive gas was also found in the mine workings. This also required a certain approach and complicated the work.
There were also human casualties. In the history of tunnel construction, there were several serious incidents related to overcoming mountain ranges. Miners often "ran into" quicksand - unstable rocks and soil. Their sudden movement led to collapses or flooding.
Experts note that such difficult natural conditions during the construction of an underground tunnel have never been encountered anywhere else in the world. But despite all the obstacles, from 1977 to 1991, Soviet engineers and builders managed to pass through over 13 thousand meters of rock. However, they were unable to complete the work before the collapse of the USSR.
They didn't build a tunnel, but they launched a bypass
The Baikal-Amur Mainline was finally launched in 1989. In order to connect the western and eastern sections of the BAM, the so-called Severomuysky bypass was commissioned back in 1983 – a winding railway with viaducts and small tunnels.
Initially, the bypass was about 25 km long, but then the access roads were widened and the length of the road increased to 64 km. This complex structure required constant repair and maintenance. Speed Train did not exceed 20 km/h. On some sections, locomotives worked in a coupling to "push" heavy carriages up the hill. Passage of passenger trains was strictly prohibited. People were transported by buses across the pass along the BAM automobile backup.

Perhaps the most iconic and recognizable object on this section is the Devil's Bridge - a viaduct 360 meters long and 35 meters high. It is located on two-tiered supports, which sway slightly when heavy trains pass. Despite this, the bridge is considered one of the most beautiful man-made objects on the BAM and still attracts travelers and enthusiasts.
It was clear to everyone that the Severomuysky bypass was only a temporary solution. No one gave up on the idea of building a tunnel. But it is important to understand that in the 90s the country had no time for some tunnel on the BAM.
But the work continued with varying degrees of intensity. In total, from 1991 to 2001, the builders covered 2216 meters and were able to perform a joint, that is, to join different sections with minimal divergence. Already in December 2001, the first train passed through the Severomuysky tunnel. But the arrangement work continued for another 2 years.
The entire construction took 26 years. At the same time, the estimated service life of the tunnel is estimated by experts at 100 years.
Technical features
After completion of construction, the total length of the single-track crossing was 15343 meters. This unique infrastructure facility became the longest railway tunnel in Russia. Today, trains cover this distance in about 25 minutes.
The builders had to meet special requirements for the reliability of all units and structures. The Severomusky tunnel is located in an extremely seismically active area. During the work alone, geologists recorded up to 1,5 thousand earthquakes annually. In addition, the movement of rocks creates colossal loads on the tunnel walls, which also required engineers to take a special approach to the construction of structures.

The water inflow in the spring months reaches 10 thousand m3/hour. Therefore, powerful water drainage installations operate in the tunnel every day, which prevent incoming water from washing out concrete structures and damaging the railway tracks. Engineers have also provided ventilation, which removes not only carbon dioxide from the passage, but also deadly radon.
The tunnel today
The Severomuysky crossing is a strategically important facility, which is guarded around the clock by both internal security and special services. In total, up to 16 pairs of trains pass through the tunnel per day. The Severomuysky bypass is also maintained in working order. This is a backup route in case of any emergency situations.
In the context of growing business activity within the country, as well as with the increase in the volume of foreign trade with Asian countries, not long ago there was talk about the necessary modernization of the BAM and the construction of a second railway tunnel.

Indeed, BAM is currently at the peak of its capacity, and the single-track Severomuysky tunnel resembles the narrow neck of an hourglass. Russian Railways has set the task of increasing BAM freight traffic to 100 million tons per year by 2050. But this figure cannot be achieved without building another underground passage in the Severomuysky Ridge area.
Both Russian Railways and a number of large mining companies in Siberia and the Far East are interested in building the new tunnel. Investors have given different figures for the cost of the project – from 60 to 259 billion rubles. But in reality the project could cost more than 500 billion.
In April 2024, on the instructions of the President, Russian Railways and Bamtonnelstroy-Most signed an agreement on the construction of the second Severomuysky tunnel. Work began in May 2024. The project is scheduled to be completed by 2032.

After the construction is completed, the capacity of the BAM will increase more than 2-fold, and together with the Trans-Siberian Railway it may even reach 270 million tons per year. There will also be no need to maintain the working condition of the external Severomuysky bypass.
Once upon a time, not all Soviet officials agreed with the need to build the BAM. They did not see any prospects. Today, the issue of increasing the capacity of this railway is acute.
All that remains for us is to thank our ancestors for such a necessary and important infrastructure facility. Let us wish good luck to the new generation of mining engineers who continue to develop the country's transport and logistics potential.
- Andrey Karpov
- vkvideo.ru
We recommend for you

A real heavyweight – the legendary helicopter has returned to the Arkhangelsk aviation fleet
This is one of the most powerful machines in the world. The civilian version will work in difficult conditions of cargo and passenger scenarios....

Now it’s official – the first look at the production Iskra and questions for AVTOVAZ
The latest innovation of the domestic company AVTOVAZ has now officially entered the serial production stage. To mark the occasion, a...

LiAZ-677: difficult restoration after 25 years of inactivity
Almost half a century after the release of the legendary LiAZ-677 of 1976, the author of a video on the YouTube channel "Bus Workshop VegaBus" decides to breathe new life into it...

"Georgian Solyanka" or Electric Locomotive 4E10
The Georgian plant TEVZ assembled many models of domestic electric locomotives during the Soviet era. In 2000, its specialists attempted to create a freight-passenger...

Verkhovyna 7 Sport – the “coolest” Lviv moped for Soviet boys
Mopeds in the late USSR were mainly represented by two factories - Lvov and Riga. Some were considered worse, others better, but the latter were on sale...

10 Tractors from the USSR That Almost No One Knows About, and in Vain
The Soviet history of tractor manufacturing contains many little-known, but in their own way brilliant machines that could have changed the industry if they had a chance to...

100-1,38 km/h in XNUMX seconds – how is this possible?
Just when it seems like the automotive industry has shown everything, something comes along that shatters the notion of what is possible. In this video, the author of the YouTube channel "Big Look...

Transmashholding has begun testing the new diesel train DP2D
He will have to travel 5000 km along the ring railway. However, the tests will not end there....

New Corvette from the USA – how much did the “pleasure” cost
"Non-standard" and flagship cars in our country now have to be "obtained". This applies to both specific models and some brands. Even if...

SJ-100 flight test numbers grow as another aircraft joins
At the same time, the exact date of the test flight of the new model became known, as well as the estimated time frame for completion of the test program. Following it –...

Serial production of the new Russian Sollers van has started
Load capacity of 800 kg and economical engine. The new van has no competitors on the Russian market....

The largest exhibition of technology in Russia has opened in Moscow
Hundreds of exhibits are a true paradise for fans of technology and mechanisms. More than 40 brands have already taken part....

Pontiac Banshee: Why was it kicked out of a New York showroom?
The turning point for Pontiac and the last chance to overtake Chevrolet. Why didn't it work out?...

Iskra is already history – AVTOVAZ presented an exclusive copy
Such Lada Iskra will exist only in a single copy. What is hidden under the cover and what symbolism is hidden in the unique modification, we offer...

How is the 18-year-old Belarusian loader better than the new "Chinese" ones?
How reliable is a forklift that can work for 18 years without losing shape? In this issue, there is an honest and detailed review of the Belarusian Amkodor 332C4,...

More Power, Less Cost – Hyundai Unveils New Platform
It is no longer "on paper", but fully implemented. The first car using this technology will be released before the end of this year....